Our Litigation Partner, Idza Hajar Ahmad Idzam, together with Senior Legal Associate, Irfan Husin Rosli and Legal Associate, Julianne John, from our Litigation Practice Group, successfully represented Medilaund (M) Sdn Bhd and Syed Jalal Syed Shuhaimi (“the Defendants”) in defending a claim before the High Court of Malaya at Klang.
The Plaintiff’s claims arose from an alleged failure to pay for additional works under a design-and-build agreement for a laundry plant, alleged unlawful termination of a maintenance agreement for the laundry machines, and defamation arising from emails sent by Medilaund’s general manager to the machines’ brand owner.
The Case
The Plaintiff alleged that the additional works were carried out pursuant to the Defendants’ instructions and that the maintenance agreement had been unlawfully terminated when it was asked to leave the project site.
The Defendants maintained that no additional works had been instructed and that the alleged works fell within the Plaintiff’s existing contractual scope under the design-and-build agreement. They further contended that asking the Plaintiff to leave the site was a reasonable mitigating measure given the unresolved issues with the machines. As to defamation, the Defendants relied on the defences of justification and qualified privilege, as the emails were communication between the machines’ user and brand owner seeking technical assistance.
The Decision
Following a full trial, the High Court dismissed the Plaintiff’s claims and partially allowed the Defendants’ counterclaim. The Court’s key findings included:
(a) Design-and-Build Contract: The agreement clearly established a design-and-build arrangement, placing responsibility for the accuracy of the relevant calculations on the Plaintiff.
(b) No Written Variation: The agreement expressly required variations to be made in writing. In the absence of any written variation order or instructions, the Plaintiff failed to establish its claim for additional works.
(c) Maintenance Agreement: The Court accepted the Defendants’ decision to ask the Plaintiff to leave the site as a mitigating measure, particularly in light of the unresolved problems with the machines.
(d) Defamation: The Court dismissed the defamation claim, finding that the emails did not contain defamatory remarks and accepting the Defendants’ justification in the circumstances.
(e) Adverse Inference: The Court also drew an adverse inference against the Plaintiff under section 114(g) of the Evidence Act 1950 for failing to call a material witness, namely its project coordinator and operations manager, without providing a cogent explanation for his absence from the witness stand.
Key Takeaways
This decision reinforces the importance of adhering to express contractual terms, particularly in design-and-build arrangements and where written variation orders are expressly required. Parties must ensure that any additional work is properly instructed and documented in accordance with the agreed contractual procedures.
The decision also highlights the importance of taking reasonable steps to mitigate losses arising from unresolved contractual or operational issues. Further, communications between a customer and a brand owner seeking technical assistance do not necessarily amount to defamation, particularly where such communications are justified and made in circumstances attracting qualified privilege.