Summary: The article analyses how Draft DAP 2026 proposes to simplify procurement categories, speed up acquisitions and prioritise Indian ownership of design know-how. It also examines the omission of the offset clause and the implication of the proposed changes for stakeholders.
Introduction
The Ministry of Defence (“MoD”), Government of India, has released a draft Defence Acquisition Procedure (“DAP”) 2026 for public and stakeholder comment. Once finalised, it will replace the DAP 2020 as the governing framework for capital acquisitions by the MoD. The draft envisages the shift of indigenisation from domestic manufacturing foreign equipment or components under DAP 2020 to Indian ownership of intellectual property (“IP”), with capital acquisitions prioritising the retention of source codes, critical design data, and upgrade authority. The draft substantially revises the process for determination of indigenous content (“IC”) through an increase in prescribed IC thresholds, tighter certification and verification requirements, and enhanced timelines, while introducing new modes of procurement such as bulk and low-cost capital acquisitions and detailed trial metrics. The draft further notes a separate aerospace acquisition procedure being developed in consultation with stakeholders will be included later in DAP 2026.
This article examines these proposed changes against DAP 2020, their likely impact on foreign and Indian original equipment manufacturers (“OEMs”),
| S.No. | Description | DAP 2020 (Erstwhile Position) | Draft DAP 2026 (New Position) | Impact |
| 1. | Acquisition Categories | DAP 2020 established five acquisition categories ranked by priority.Buy (Indian-IDDM), Buy (Indian), Buy and Make (Indian), Buy (Global-Manufacture in India), and Buy (Global). | The draft reduces procurement categories to four.Removes the Buy (Indian) category and renames Buy and Make (Indian) to Buy (Indian) and Manufacture in India. | Buy (Indian-IDDM) was already the top procurement preference, but the Buy (Indian) route let qualifying Indian subsidiaries of foreign OEMs supply locally manufactured products using foreign technology. Removing this route shifts suppliers to the combined Buy (Indian) and Manufacture in India category, requiring both local manufacturing and technology transfer. This signals a shift that reflects the draft’s broader emphasis on placing IP on equal footing with domestic manufacturing. For industry players, this favours Indian suppliers with indigenous design (“ID”) capabilities and encourages foreign OEMs to negotiate technology-transfer partnerships rather than rely solely on local manufacturing. |
| 2. | Indigenous Content Requirement | The minimum final-stage IC requirement under Buy (Indian-IDDM), Buy and Make (Indian) and Buy (Global-Manufacture in India) was 50%. An IC certificate by a “Responsible Designated Official” must accompany each delivery. | IC is up from 50% to 60% under these categories, with incentives including a price credit of up to 15% for higher localisation.Now all deliveries, including batches/lots, must have an IC certificate for that batch/lot and a cumulative IC for all previous deliveries. | The draft raises the overall IC threshold across the relevant Buy categories and increases the verification burden for both vendors and sub-vendors. |
| 3. | Design Ownership / IP Focus | For Buy (Indian-IDDM), vendors furnished an ID undertaking stating the design was “partly or wholly” owned by them or an Indian entity, which covered rights to manufacture, support, modify, and upgrade, subject to disclosed encumbrances, and permitted technical verification.Submission of a false undertaking “at any post contract stage” may make the vendor liable to forfeiture of the performance-cum-warranty bank guarantee (“PWBG”) for ID non-compliance.It only distinguished “owned” from “licensed” rights, leaving “acquired rights” unaddressed. | Draft DAP 2026 defines ID as ownership of the main equipment, system, or platform design originally conceived and developed in India by an Indian vendor, design agency, or entity owned and controlled by resident Indian citizens.It requires comprehensive ownership and control over design constituents and technical artefacts like drawings and source codes, and unrestricted rights to manufacture, support, modify, upgrade, develop next-generation versions, and export (with Indian government approval), without foreign OEM dependence.It also mandates completing MoD verification within two years of contract signing. Where verification is required or initiated, PWBG release depends on its completion; failure to establish Indian design ownership within that period triggers forfeiture.Fully acquired foreign design/IP rights qualify as ID only if all criteria are met, including the right to modify, upgrade and develop next-generation versions independent of foreign OEMs. | Foreign OEMs seeking to participate through the Buy (Indian-IDDM) route must support their bids through acquired IP by transferring ownership and independent development rights to an Indian partner, as foreign technology licence is no longer sufficient.Retaining design rights with Indian entities ensures strategic autonomy over maintenance, upgrades, and export of derivative platforms without foreign OEM permission.Supporting evidence like the undertaking and its scrutiny is now tied to a stricter ID definition and extends verification across design and production tiers.This strengthens Indian players’ bargaining position in partnership and technology-transfer negotiations, but foreign OEMs may hesitate to transfer proprietary IP to Indian partners, potentially discouraging their participation. |
| 4. | New Procurement Procedures | Several procurement categories and sub-categories were listed. Fast-track procedure (“FTP”)was providedfor urgent operational procurement, including where normal timelines impaired readiness. However, it significantly overlapped with the procurements under the existing routes such as the Buy categories and was not a general low-value procurement route for trying limited quantities before bulk procurement. | High tech and capital-intensive equipment are required on a long-term basis, with regular upgrades. Long-term bulk acquisition (“LTBA”) from Indian and foreign OEMs in multiple tranches has been introduced with each tranche acceptance of necessity (“AoN”) specifying only the part-quantity. SQRs are upgraded tranche-wise.Low-cost capital acquisition (“LCCA”) is capped at INR 75 crore per project with an annual ceiling of INR 2,000 crore, but procurement is restricted to the Buy (Indian-IDDM) and Buy (Indian) and Manufacture in India categories and exempted from the RFI, SQR formulation, and trial stages.Other capital procurement procedure (“OCPP”) covers capital expenditure to enhance existing assets, including overhauls, refits, upgrades, refurbishment, and replacement of unserviceable units. | LTBA supports sustained production through successive tranches. LCCA provides a simpler route to limited indigenous orders before possible bulk procurement, without requiring an FTP-type operational urgency. It omits RFI, SQR formulation, and trials, but retains evaluation and approval requirements; subsequent bulk orders are not guaranteed.OCPP provides an asset-support route, rather than a general emergency or unconventional-procurement category. |
| 5. | Innovation (iDEX) and Make Procedure | iDEX/Make prototypes had no assured pathway to a production order.Efforts should be made to have more than one development-cum-production partner (DcPP).If only one DcPP was recommended, the Defence Research and Development Organisation (“DRDO”) merely had to “justify the same” to the AoN-according authority, i.e., discretionary standard. | The draft provides five years of assured orders for successful Make/iDEX prototypes.It requires “minimum two” DcPPs, specifically “one from PSU/DPSU and one from private industry” (or both from private industry if no DPSU is available).A single DcPP now requires specific justification in the Statement of Case; specific approvals must be sought. | The assured-order guarantee combined with LTBA should reduce procurement uncertainty and facilitate commercial viability for smaller players to invest in developing defence technology.The DcPP selection review ensures that once a technology reaches the DRDO development-to-production stage, the choice of manufacturer does not default unfairly to a narrow set of incumbents. |
| 6. | Acquisition Timelines | The procurement cycle for complex platforms ran through a long, multi-stage sequence from AoN to contract signing, causing significant contract execution delays. Monitoring of timelines from the RFI stage was also not mandated.Under the FTP, approval in principle (“AIP”) was non-existent, with a 45–90-day window to complete bid submission and technical/on-site evaluationtogether. Overall pre-delivery cycle had to be completed within 216 days. | The draft mandates monitoring of timelines from the RFI stage onwards. Non-submission of the Statement of Case within 15 months of the RFI triggers a process restart. When the government seeks information, companies must respond within 2–4 months.AIP is introduced before AoN under FTP, and the period for bid submission and technical/on-site evaluationis now 14 days, with all approvals now running in parallelly rather than sequentially. Overall time is now 119–126 days. | This imposes hard deadlines and prevents delay from either side: the 15-month RFI-to-Statement-of-Case deadline binds the government’s own internal processing, while the 2-4-month response window binds vendors when the government seeks information. For FTP, overlapping steps are the main mechanism compressing the total timeline, while delivery timelines after contract signing remain capped at the same 104 weeks. |
| 7. | Offset Obligations | The standalone Offset Guidelines chapter treats 30% IC as an alternative to discharging offset obligations.The Offsets clause is applicable for Buy (Global) categories of procurement where the estimated AoN cost is INR 2000 crore or more. | The draft proposes removing offsets entirely, with the 30% IC threshold as the sole India-content obligation for Buy (Global) and no offset fallback for shortfalls.Existing offset obligations are grandfathered under the older regime. | This provides foreign OEMs potential relief from the administrative burden, banking compliance, and penalty exposure that accompanied offset obligations.The benefits arising from the removal of offsets appear to be balanced with the IC requirements of up to 30% (not a minimum but a ceiling/target). |
| 8. | Leasing as an acquisition category | Leasing was added only as a limited category (Lease (Indian) and Lease (Global)), with no dedicated sub-typing of lease structures.Lease-vs-buy cost–benefit analysis was not mandatory in the Statement of Case. | Leasing is formalised as a standalone acquisition category, in a dedicated Chapter X. The draft defines Operating Lease (with Dry, Wet, and Damp sub-variants) and Finance Lease as distinct lease types.A cost–benefit analysis is mandatory in the Statement of Case. | Leasing with its own chapter gives procurement officers and industry a settled rulebook to structure deals against.The framework enables tailored deal structuring, such as wet leases to bridge capability gaps with crew bundled in, or finance leases when eventual ownership is the goal, reducing ambiguity in RFI/RFP drafting. |
Conclusion
The draft signals a shift towards Indian design ownership, independent upgrade capability, and greater domestic value addition. Its categorisation and verification rules make design sovereignty a commercial consideration for Indian suppliers and foreign OEMs. The final procedure may differ following consultation and approval, but the draft indicates the government’s direction towards greater defence self-reliance and technological autonomy.

For further information, please contact:
Ankita Kumar, Partner, Cyril Amarchand Mangaldas