In Lockheed Martin Aeronautics Company, ASBCA No. 62209 (a C&M case), the Armed Services Board of Contract Appeals (Board) held that the contractor’s claim, seeking recovery for impacts of over-and-above repair work during contract performance, was timely filed under the Contract Disputes Act’s six-year statute of limitations—rejecting an Air Force Motion for Summary Judgment and granting cross-motions filed on behalf of Lockheed Martin.
Recognizing that a contractor’s claim cannot accrue before the events that fix the liability of the government, the Board held Lockheed Martin’s claim did not have a single accrual date but, rather, multiple accrual dates based upon when the government approved each repair.
The Board separately held that those government approvals represented “the type of single-topic . . . yet repeated and distinct events” making Lockheed Martin’s claims timely under the well-recognized “continuing claim doctrine.”