Introduction
After winning reelection on October 25, 2026, Brazilian President Lula said in a speech that Brazil should leverage its renewable energy potential to attract data centers, and argued that part of the related infrastructure capacity should be reserved for Brazilian data.1Brazil wants to become a data center hub, and it has good arguments: the largest digital market in Latin America, an electricity mix that was 86.8% renewable in 2025 and direct submarine cable links to North America, Europe and Africa.2
In recent years, Chinese companies have been steadily expanding their business footprint in Brazil’s technology, media and telecommunications (TMT) sector, with cloud services and Internet data center (IDC) infrastructure playing an increasingly important role. Some Chinese companies are already providing local cloud services and building data centers in Brazil, offering cloud services and digital solutions to local customers, with projects spanning digital infrastructure deployment and the delivery of services tailored to the Brazilian market. As the application of artificial intelligence, cloud computing and digital business models drives demand for computing power and data storage, Brazil is attracting a growing number of Chinese companies seeking to invest in data centers through project development, M&A and partnerships.
Since 2025 Brazil has started to build a legal framework for the sector. For a foreign investor, the rules are spread across several laws and authorities, and some are still being written. This is especially relevant for Chinese investors, already present in Brazilian cloud services, equipment manufacturing and the power sector, whose investments may also benefit from the Brazil–China double taxation treaty, as amended by a protocol promulgated in 2025.
This guide maps out the key legal, regulatory and transaction-structuring issues involved in investing in data centers in Brazil, to assist investors in making prudent decisions and effectively advancing project implementation. Jointly prepared by lawyers from JunHe and Mundie Advogados based on their practical experience, it discusses each of the following issues which an investor usually encounters: the market, the institutions, taxes, electric power, permits, telecom and data rules, and the structure of the investment itself.
1. Why Brazil
Brazil accounts for roughly half of Latin America’s installed data center capacity, measured in megawatts. According to the Brazilian government’s 2025 assessment, approximately 60% of the country’s digital workloads depend on services provided from abroad; expanding domestic capacity has become an explicit policy goal.3 Large cloud providers are expanding their Brazilian operations. Chinese groups are already present across cloud services, equipment manufacturing, power generation and transmission, and international connectivity.
Fortaleza is Brazil’s main submarine cable hub, with direct connections to North America, Europe and Africa, reinforcing its attractiveness for data center investments.
2. How the system works
Brazil is a federation. The federal government sets the rules for telecommunications, energy, data protection and most taxes; the 26 states and the Federal District issue most environmental licenses and collect their own value-added tax (ICMS); and municipalities decide zoning. Laws are passed by the Congress, but the President may also issue provisional measures, which take effect immediately and lapse unless the Congress converts them into law within the applicable constitutional period (normally up to 120 days, excluding congressional recesses). Much of the day-to-day regulation is done by independent agencies. These are the bodies a data center investor is most likely to deal with:
Institution
Role for a
data center investor
Anatel (telecommunications agency)
Authorizes telecom services and certifies network equipment
ANEEL and ONS (electricity regulator and grid operator)
Connection to the grid and allocation of transmission capacity
RFB (Brazilian Federal Revenue Service)
Grants REDATA qualification and co-qualification to eligible companies
ANPD (data protection agency)
Enforces the data protection law, including international transfers
State environmental agencies
Environmental licenses; water permits come from water authorities
CADE (antitrust authority)
Reviews notifiable acquisitions and joint ventures before closing, based on turnover thresholds and other statutory criteria.
Central Bank
Receives mandatory foreign investment reports under the applicable rules
BNDES (national development bank)
Long-term financing, including credit lines for data centers
3. Taxes: the REDATA regime
Taxes on equipment have long been a significant concern about building data centers in Brazil; according to the government, they made operating here about 30% more expensive than abroad. The taxes involved are federal: PIS and Cofins, two contributions charged on revenue and imports; IPI, an excise tax on manufactured goods; and import duty.
REDATA, the special tax regime for data center services established by Law No. 15,504 of September 2026, works as a trade-off: eligible companies obtain suspension of the specified taxes on qualifying ICT equipment, subject to qualification and other requirements, and commit to a set of targets. The suspension is converted into a zero tax rate upon fulfilment of the applicable statutory conditions.4
What the project gets
What the project must do
Suspension of the specified PIS/Cofins, IPI and import-duty charges on eligible ICT equipment, subject to qualification and other requirements
Make at least 10% of the benefited services available to the Brazilian market, or invest an additional 10% of the value of benefited products in research, development and innovation
Conversion of the suspension into a zero tax rate upon fulfilment of the applicable statutory conditions
Meet sustainability criteria; source all electricity from renewable or low-emission generation; maintain annual water usage effectiveness at or below 0.05 liters per kWh
A 20% reduction in the domestic-market and ordinary 2% research commitments in the North, Northeast and Center-West
Invest 2% of the value of benefited products in research, development and innovation, and publish a sustainability report
Two features matter particularly for foreign groups. Manufacturers contractually supplying ICT products they manufacture to qualified beneficiaries may obtain co-qualification, with relief on inputs used in those products. Any qualified company may replace the domestic-market commitment with the additional research investment described above, an option of particular interest to projects serving a group’s global workloads. Import-duty relief is limited to eligible products without equivalent domestic production.5
The statutory time limits are important. Under the REDATA law, the PIS/Cofins and IPI benefits apply only until December 31, 2026. Import-duty relief is subject to the regime’s five-year term and limited to eligible products without equivalent domestic production, as listed by the Executive Branch. From January 1, 2027, PIS and Cofins are replaced by CBS; REDATA benefits do not extend to CBS or IBS under Brazil’s consumption tax reform.6
In practice: access to REDATA relief is not automatic. Qualification or co-qualification by the RFB, inclusion of the relevant products on the applicable lists and compliance with implementing rules should be confirmed before the incentives are included in project financial models.
4. Power: grid access and supply
A large data center can consume as much electricity as a small city, and power is a key constraint in Brazil. Large consumers can buy electricity directly from generators on the free market or invest in their own generation (self-production), but grid access must be assessed separately from energy procurement. In early 2026, ONS accepted for processing data center access requests totaling approximately 7 GW. Acceptance of these requests did not constitute technical approval or a guarantee of grid connection.
Under Decree No. 12,772/2025, transmission grid capacity is allocated through periodic access rounds, with competitive allocation where demand exceeds available capacity. In the first competitive process, held in October 2026, data centers were allocated all 228 MW of transmission grid capacity made available in São Paulo.7 Under the rules introduced by Law No. 15,269/2025, a consumer may qualify as a self-producer through certain equity or corporate relationships with an authorized or concession-holding generation company. Among other requirements, and subject to applicable grandfathering provisions, the regime requires at least 30 MW of aggregate contracted demand, comprising only consumer units of at least 3 MW each, and qualifying direct or indirect voting equity interests or other specified corporate relationships. The extent of the self-producer treatment is limited to the lower of the energy allocated for the consumer’s own use and the energy corresponding to its participation in the generation project. Special rules apply to certain structures involving non-voting shares. These conditions should be considered when structuring a joint venture with a generator.8
In practice: grid access and power procurement should be assessed alongside land rights and environmental licensing before material capital commitments are made.
5. Permits and land
Most data centers need an environmental license, usually issued by the state environmental agency, and, depending on how the project uses and discharges water, a water-use permit. Because licensing is largely a state matter, the rules vary across the country. Ceará, in northeastern Brazil, adopted legislation in July 2026 establishing environmental licensing procedures tailored to the size, location and potential environmental impact of data center projects. About 20 bills on data centers were pending in state assemblies in October 2026. The national environmental council has called for national guidelines to address the risks of inconsistent environmental standards.9
Land needs early attention too. Brazilian law restricts the acquisition and lease of rural land by foreigners, and in April 2026 the Supreme Court confirmed that these restrictions also apply to Brazilian companies controlled by foreigners. Though urban land is outside that rural-land regime, inclusion within a municipal urban perimeter does not, by itself, settle the land’s classification. Due diligence should cover classification, title, encumbrances, zoning, access rights and the suitability of the land rights for project financing, including any special restrictions affecting the site.10
Environmental due diligence should assess the required studies and any applicable community-consultation obligations, as well as the risk of administrative or judicial challenges.
6. Telecom and data rules
Running a data center is not, in itself, a telecommunications activity. Colocation, hosting and cloud services are classified as value-added services, which do not in themselves require an Anatel authorization; a company that also provides regulated connectivity services needs the applicable authorization, available to a company incorporated in Brazil with its head office and management in the country, whatever the origin of its capital. Anatel has nevertheless sought to bring data centers closer to its oversight. In 2025 it introduced a conformity-certification requirement for data centers integrating telecom networks. Implementation of that requirement was suspended in early 2026, and the agency has also been reviewing cybersecurity rules relevant to these facilities. Network equipment subject to Anatel’s conformity-assessment regime must meet the applicable requirements before it is sold or used in Brazil.11
On data, Brazil’s general data protection law (LGPD) follows the European model. Its enforcer, the ANPD, became a regulatory agency under a provisional measure in 2025, converted into law in 2026. In January 2026 Brazil and the European Union recognized each other’s regimes as adequate. There is no general rule requiring all data to be stored in Brazil, but special rules apply to classified information of the federal public administration: top-secret information may not be processed in the cloud, while information at the reserved and secret levels may use qualifying private or community clouds, subject to Brazilian-location, provider-qualification and security requirements and narrowly defined exceptions.12 International transfers deserve a closer look. Under the LGPD, personal data may leave Brazil only on the grounds provided by law, including an adequacy decision, the ANPD’s standard contractual clauses, or specific clauses or binding corporate rules approved by the ANPD. Other grounds include the data subject’s specific consent and certain transfers necessary for contract performance. The standard clauses must be adopted without changes. Since China has no adequacy decision, groups replicating data to China or allowing access from abroad should assess the transfer mechanism for each data flow; binding corporate rules require prior ANPD approval. A pure colocation provider that only hosts clients’ equipment will usually not itself transfer personal data, but the analysis depends on the activities actually performed.13
In practice: assess the security and resilience obligations in contracts with telecom operators, and plan international data flows around the LGPD’s transfer rules.
7. Structuring the investment
Brazil’s corporate framework is open to foreign capital, and there is no cap on foreign ownership of data center companies. Projects are usually held through a special purpose company for each site, organized either as a limited liability company (limitada), which is simpler to run, or as a corporation (sociedade anônima), which is better suited to issuance of project bonds and new investors. Foreign shareholders must obtain the applicable Brazilian taxpayer identification (CNPJ for entities; CPF for individuals) and appoint a local attorney-in-fact. Foreign investment is subject to the applicable Central Bank reporting requirements, including SCE-IED reporting where the relevant thresholds and conditions are met. Transactions that constitute notifiable concentrations, including qualifying acquisitions and joint ventures, require CADE clearance before closing. The current turnover thresholds are at least R$750 million for one participating economic group and R$75 million for another, in Brazil in the preceding year.14
On tax, Brazil generally imposes a 10% withholding tax on dividends paid abroad since January 2026, subject to applicable domestic exemptions and transitional rules. Under the Brazil–China double taxation treaty, as amended by the protocol promulgated in 2025, a 10% ceiling applies where the beneficial owner is a company directly holding at least 10% of the payer’s capital throughout a 365-day period that includes the dividend payment date; the treaty provides a 15% ceiling in other cases. A 5% ceiling applies to certain qualifying governmental entities and designated institutions, subject to the applicable conditions. These treaty ceilings do not increase a lower rate provided by Brazilian domestic law. The treaty generally caps withholding on interest at 15%, reduced to 10% for qualifying bank loans with a term of at least five years used, among other specified purposes, to finance equipment acquisitions. Interest paid to certain qualifying Chinese governmental entities and financial institutions may be exempt from Brazilian withholding tax, subject to the conditions applicable to each beneficiary. Treaty relief for Brazilian-source income depends on the recipient qualifying as a resident of China for treaty purposes, the applicable beneficial-ownership requirements and anti-abuse provisions, including limitation-on-benefits and principal-purpose-test rules. An intermediate holding company in a third jurisdiction does not automatically qualify for these benefits.15
An intermediate holding company does not, by itself, remove US export-control restrictions on advanced chips. Their application may depend on the products, end use, recipients and ultimate parent, and should be assessed separately under US law.16
The transaction structure should reflect the project’s stage of development. For an operating business, due diligence should test the reliability of revenues, compliance history, customer commitments and remaining capital expenditure. For a development-stage project, the critical question is which land, power and licensing rights have actually been secured, by whom and on what conditions. A share acquisition and an acquisition of assets or project rights require different transfer and consent analyses; neither should be assumed to preserve every permit, contract or tax qualification without further review.
Investment documents should distinguish capital deliberately exposed to development risk from funding conditional on agreed milestones. Grid access, land rights, permits and any tax qualification on which the investment case depends may justify conditions precedent, staged payments or deferred funding. The documents should identify who must secure each item, the evidence of completion and the consequences if agreed deadlines are missed. Representations, indemnities and security for performance should address identified liabilities and execution risks; they do not replace the rights and approvals needed to build and operate the project.
In a joint venture, the shareholders should agree how budgets, additional funding, cost overruns and delays will be handled, including the consequences of a failure to contribute. Where a partner also supplies land, power or services, its roles as shareholder and counterparty should be addressed together. Approval and monitoring of related-party contracts, conflicts of interest and contractual remedies warrant particular attention. Deadlock and exit arrangements should preserve workable decision-making and essential services, rather than assume that a shareholder dispute can be resolved without affecting the project.
Construction, equipment, power and customer contracts should be reviewed against a common delivery timetable. Completion tests, energization and the customer’s service commencement date may depend on different parties; gaps between those obligations should be identified before commitments are made. Service levels, remedies, liability caps, insurance and security for performance should be coordinated, without assuming that identical terms can be imposed throughout the contractual chain. The allocation of delay and regulatory risks should also address the financial consequences of losing tax benefits and the records needed to demonstrate compliance with the relevant commitments.
Financing and exit arrangements deserve attention at the structuring stage. The proposed security package, assignment rights and any lender step-in arrangements should be tested against the company’s land rights, key contracts and applicable rules. Financing maturity and repayment assumptions should also be assessed against the duration and termination rights of customer and supply contracts. Transfer restrictions and exit mechanisms in the shareholders’ agreement should be coordinated with lender consents and change-of-control clauses in project contracts. A sale of shares should not be assumed to avoid consent requirements merely because the contracting company remains the same.
8. Developments to monitor
Investors should monitor the following developments:
- REDATA implementing measures, qualification procedures and eligible-product lists, including those relevant to import-duty relief after 2026.
- Anatel’s next step on data center certification and cybersecurity.
- Bills in Congress, including a national data center policy with special zones and “data embassies” (PL 1680/2025), rules for AI data centers (PL 3018/2024) and a mechanism to screen foreign investment in strategic sectors (PL 1051/2025).17
- Administrative and judicial developments affecting environmental licensing.
9. Conclusion
For Chinese investors, policy continuity is of great importance: China has been Brazil’s largest trading partner since 2009, and the two countries have established cooperation initiatives in the digital economy.18 These ties provide a basis for continued cooperation.
Turning that cooperation into viable projects, however, will depend on the implementation of the remaining regulatory measures, including those relating to REDATA and Anatel’s framework for data centers, as well as on securing the essential elements of each project: reliable power, suitable land rights, the necessary permits and well-structured contractual arrangements. Companies in the telecom and digital infrastructure sector should also take part in shaping the evolving rules, including through Anatel’s public consultations.
* This article reflects publicly available information as of October 26, 2026 and does not constitute legal advice. It was supported by interns of JunHe LLP, Yijia Wu and Jingxian Zhang, and Giovanna Gomes Soares of Mundie Advogados to whom we express our gratitude.

For further information, please contact:
DU, Lijing, Partner, JunHe
[1] October 25, 2026 Agência Brasil report on President Lula’s remarks https://agenciabrasil.ebc.com.br/politica/noticia/2026-10/vamos-mudar-o-jeito-de-governar-este-pais-diz-lula.
[2] EPE, National Energy Balance 2026, Summary Report (base year 2025), official release of June 3, 2026; Etice, “Etice apresenta, na África do Sul, vantagens competitivas do Ceará para atração de data centers” (Nov. 11, 2025).
[3] S&P Global, “Brazil leads Latin America in data center growth on renewable energy” (Aug. 27, 2026), reporting JLL Research’s installed-capacity figures; Explanatory Memorandum EMI No. 00010/2025 MDIC/MF/MME (Sept. 16, 2025), accompanying Provisional Measure No. 1,318/2025.
[4] Law No. 11,196/2005, Articles 11-A to 11-J, particularly Article 11-C, §§8 and 9, as amended by Law No. 15,504 of September 15, 2026.
[5] Law No. 11,196/2005, Articles 11-A, §§2 and 6, 11-B, §§1, 5 and 6, 11-C, §§3 and 6, and 11-D, as amended by Law No. 15,504/2026.
[6] Law No. 11,196/2005, Articles 11-B, 11-C and 11-J, as amended by Law No. 15,504/2026; Constitutional Amendment No. 132/2023; Complementary Law No. 214/2025.
[7] ONS, official notices on data center access requests (notice 12390: https://www.ons.org.br/paginas/noticias/details.aspx?i=12390) and the first competitive allocation of transmission grid capacity (notice 13357: https://www.ons.org.br/paginas/noticias/details.aspx?i=13357); Decree No. 12,772/2025.
[8] Law No. 9,074/1995, Article 16-B, as amended by Law No. 15,269/2025.
[9] Law No. 15,190/2025; Law No. 9,433/1997, Articles 12 and 13; Ceará Law No. 19,849/2026, Articles 3–6; Times Brasil (Oct. 13, 2026); CONAMA Motion No. 147/2026.
[10] Law No. 5,709/1971; Law No. 8,629/1993, Article 23; Law No. 6,766/1979, Article 53; Federal Supreme Court, ADPF 342 and ACO 2463 (Apr. 23, 2026); INCRA, guidance on rural-land reclassification (Descaracterização de Imóvel Rural).
[11] Law No. 9,472/1997, Articles 61 and 133; Anatel Resolution No. 780/2025; Acórdãos No. 42/2026 and 58/2026; Anatel Public Consultations No. 48/2025 (data center technical requirements and conformity assessment) and No. 32/2025 (revision of the Cybersecurity Regulation).
[12] Law No. 13,709/2018 (LGPD); Provisional Measure No. 1,317/2025, converted into Law No. 15,352/2026; Resolution CD/ANPD No. 32/2026; GSI/PR Normative Instruction No. 8/2025.
[13] Law No. 13,709/2018, Article 33; Resolution CD/ANPD No. 19/2024.
[14] RFB Normative Instructions No. 2,119/2022 and No. 2,172/2024; Law No. 14,286/2021; BCB Resolution No. 278/2022; Law No. 12,529/2011, Articles 88 and 90; Interministerial Ordinance MJ/MF No. 994/2012.
[15] Law No. 9,249/1995, Article 10, as amended by Law No. 15,270/2025; Brazil–China tax treaty, Articles 10, 11 and 26-A, as amended by the protocol promulgated by Decree No. 12,620/2025.
[16] US Bureau of Industry and Security, Guidance Regarding Enforcement of License Requirements for Advanced Computing Items for Entities Headquartered in Country Group D:5 and Macau (May 31, 2026).
[17] Agência Câmara (June 2026); Senate records for PL 3018/2024; Chamber records for PL 1051/2025.
[18] Ministry of Communications (Nov. 2024), on bilateral digital-economy cooperation; Rádio Senado (Apr. 8, 2025), on Brazil–China trade relations.